NORDIC PROCUREMENT ENFORCEMENT
  LEGAL RESEARCH PROJECT
   

   
 
 
 
    
 
 
Previous
Up
Next
   
   
c3-28.1
c3-28.2
u1-15.stm
c3-29
c3-30.1.s1
c3-30.1.a
c3-30.1.b
c3-30.1.c
c3-30.1.d
npl2-12.3.p2+4-5
c3-30.2-4
npl2bk2-2.3
c3-31.s1
c3-31.1.a
c3-31.1.b
c3-31.1.c
c3-31.2.a
c3-31.2.b
c3-31.2.c
c3-31.2.d
c3-31.3
c3-31.4.a
c3-31.4.b
u3-40.3.i
u3-40.3.j
g1-6.1.h
w1-9.2
c3-32.1
c3-32.2.1
c3-32.2.2.s1
c3-32.2.2.s2
c3-32.2.3
c3-32.2.4
c3-32.2.5
c3-32.3
c3-32.4.1
c3-32.4.2
c3-33.1
c3-33.2
c3-33.3
c3-33.4
c3-33.5
c3-33.6
c3-33.7
c3-34.1-2
c3-34.3

32004L0018: c3-34.1-2

Special award procedure

EU Law Community DK Law EU Cases DK Cases

EU Law

32004L0018 - Classic (3rd generation) Article 34.1-2
Article 34
    Public works contracts: particular rules on subsidised housing schemes
    In the case of public contracts relating to the design and construction of a subsidised housing scheme the size and complexity of which, and the estimated duration of the work involved require that planning be based from the outset on close collaboration within a team comprising representatives of the contracting authorities, experts and the contractor to be responsible for carrying out the works, a special award procedure may be adopted for selecting the contractor most suitable for integration into the team.
    In particular, contracting authorities shall include in the contract notice as accurate as possible a description of the works to be carried out so as to enable interested contractors to form a valid idea of the project. Furthermore, contracting authorities shall, in accordance with the qualitative selection criteria referred to in Articles 45 to 52, set out in such a contract notice the personal, technical, economic and financial conditions to be fulfilled by candidates.
31993L0037 - Works (2nd generation) Article 9.1-2
Article 9
In the case of contracts relating to the design and construction of a public housing scheme whose size and complexity, and the estimated duration of the work involved, require that planning be based from the outset on close collaboration within a team comprising representatives of the contracting authorities, experts and the contractor to be responsible for carrying out the works, a special award procedure may be adopted for selecting the contractor most suitable for integration into the team.
In particular, contracting authorities shall include in the contract notice as accurate as possible a description of the works to be carried out so as to enable interested contractors to form a valid idea of the project. Furthermore, contracting authorities shall, in accordance with Articles 24 to 29, set out in such a contract notice the personal, technical and financial conditions to be fulfilled by candidates.

EU Cases

Case PteRefText