NORDIC PROCUREMENT ENFORCEMENT
  LEGAL RESEARCH PROJECT
   

   
 
 
 
    
 
 
Previous
Up
Next
   
   
c3-35.1.1.a.1
c3-35.1.1.a.2
c3-35.1.1.b
c3-35.1.1.c
c3-35.1.2
c3-35.1.3
c3-35.1.4-6
u3-41.2
u3-41.3
c3-35.2
c3-35.3
u3-42.3.a-b
u3-42.3.c.s1
u3-42.3.c.s2
c3-35.4.1
c3-35.4.2-3
c3-35.4.4
c3-35.4.5
u3-43.3
u3-43.5
c3-36.1
u2-25.3.s3
c3-36.2.1
c3-36.2.2
c3-36.3.1
c3-36.3.2
c3-36.4.1
c3-36.4.2
c3-36.5
c3-36.6
c3-36.7
c3-36.8
c3-37

32004L0018: c3-35.1.3

Sent to the Commission or published

EU Law Community DK Law EU Cases DK Cases

EU Law

32004L0018 - Classic (3rd generation) Article 35.1.3
The notice referred to in subparagraph (c) shall be sent to the Commission or published on the buyer profile as soon as possible after the decision approving the planning of the works contracts or the framework agreements that the contracting authorities intend to award.
32004L0017 - Utilities (3rd generation) Article 41.1.3
The notice referred to in subparagraph (c) shall be sent to the Commission or published on the buyer profile as soon as possible after the decision approving the planning of the works contracts or the framework agreements that the contracting entities intend to award.
31993L0037 - Works (2nd generation) Article 11.7.2
The notice referred to in paragraph 1 shall be sent as soon as possible after the decision approving the planning of the works contracts that the contracting authorities intend to award.
31989L0440 - Fourth amendment of Works (1st generation) Article 1.12=W1-12.6.a
(a) The notice referred to in paragraph 1 shall be sent as soon as possible after the decision approving the planning of the works contracts that the contracting authorities intend to award;